Bunker update

The left side bunker revealed many a surprise as we removed the massive amounts of old sand.

LS 16 tree roots

LS 16 large tree roots

16 LS bunker old pipe

And we are not the first ones to work in this bunker as we discovered an old obsolete drain line.

16 LS bunker old drainge

With all the old sand removed, we are now ready to reshape the bunker. I have consult with Wayne Morrison, he is an William Flynn historian, who concurred with me that the original bunker was much shorter and wider back in the day. So my plans are to restore the bunker back, as close as possible, to its original design using the aerial photos from the 1930’s that you see hanging in the grill room. Doing so will also provide better surface drainage and wider egress to and from the rear of the green.

 

 

Project update.

We are very close to wrapping up the 3 winter projects. Working on projects this time of year always takes longer than expected as maintaining the golf course is our priority everyday in season. Add in some wet weather, outings, and unexpected setbacks(cutting the 4″ irrigation main behind 3 green last Wednesday as an example) can add time to the most conservative deadline.

Here is were we stand on the projects.

Fan at #3 green. The electric line was installed and inspected last week. We will be pouring the concrete mounting pad this week. The concrete will need a week to cure before we can mount the fan and have the electrician return for the final hook up. Once that passes inspection, I will submit a request to PECO for a meter.

Stairs at 4 green. The landing areas will be filled with a material called Porous Pave. Its composed of recycled tires and a binding polymer that allows water to flow through it. I’ve seen this material used with success at Fieldstone GC last fall. Renting a small mixer is required and will be used in conjunction with pouring the pad for the fan at 3 green this week. The next step will be installing the hand rail which will be completed by May 26.

Bunkers at 16 green. Rebuilding of the left side bunker has begun. I saved this one for last as its going to be the most challenging. And it hasn’t disappointed! The bunker is extremely deep as we determined after removing the old sand. And judging by the layers of sand on the back side, the bunker was much larger back in the day. Play-ability is the priority when we rebuild bunkers. We also consider the original design of the feature and lastly, the ongoing maintenance involved. So for this one I’m going to consult with a couple of industry experts to get other opinions. I’d like your opinion too! So please feel free to comment on this bunker and any other golf course related topic. In the meantime, we will be moving forward with completing the clean out and determining where the original bunker once stood.

Please check back for updates as I plan to blog on a regular basis. Thank you for your patience while we finish up these projects.

Jay Parisien CGCS